Work already booked
Nebius has signed about 16 years of its current sales. Microsoft, about 2. The small clouds sold furthest ahead.
The full story
A backlog is contracts signed but not yet delivered. Divide it by a year of sales at today's pace and you get how far ahead a company has sold.
Backlog vs latest quarter's revenue × 4:
Nebius - $37.5bn vs ~$2.3bn a year. ~16 years. CoreWeave - $103.7bn vs ~$10.3bn. ~10 years. Oracle - $664bn vs ~$77bn. ~8.6 years. Google Cloud - $514bn vs ~$99bn. ~5.2 years. AWS - $496bn vs ~$169bn. ~2.9 years. Microsoft - $678bn vs ~$360bn. ~1.9 years.
Microsoft, Amazon and Google fund new data centers from cash their other businesses make (Oracle's free cash flow was −$5bn last quarter). The two neoclouds at the top mostly don't have that cushion: CoreWeave carries about $35bn of debt and lost $626m last quarter; Nebius plans $20–25bn of capex this year on $3–3.4bn of revenue. A backlog becomes money only once the data centers run.
Fast growth shrinks the ratio: at Nebius's $7–9bn year-end run-rate target it would be 4 to 5½ years. And CoreWeave's largest customer was 40% of its first-half revenue.
Microsoft's figure is business customers only; Amazon's is "primarily AWS". Quarters end 30 Jun 2026, Oracle's 31 Aug.
Want to see how this looks now?
Where the numbers come from
Show all 25 sources
- www.sec.govsec.gov
- www.sec.govsec.gov
- www.sec.govsec.gov
- www.sec.govsec.gov
- www.boerse-express.comboerse-express.com
- nebius.comnebius.com
- www.sec.govsec.gov
- www.techrepublic.comtechrepublic.com
- www.datacenterdynamics.comdatacenterdynamics.com
- finance.yahoo.comfinance.yahoo.com
- aibusiness.comaibusiness.com
- longyield.substack.comlongyield.substack.com
- www.digitimes.comdigitimes.com
- intuitionlabs.aiintuitionlabs.ai
- the-decoder.comthe-decoder.com
- idahobusinessreview.comidahobusinessreview.com
- www.fool.comfool.com
- techcrunch.comtechcrunch.com
- storyboard18.comstoryboard18.com
- www.nasdaq.comnasdaq.com
- heise.deheise.de